8 Inspection, Testing and Preparation for Shipment
8.2 Inspection
8.2.1 General
Add to item c.
Final assembly maintenance and running clearances for bearings and seals shall be submitted with as built data. 8.2.2 Material Inspection
Add to section
Material certificates shall be provided in accordance with Annex B of S-612Q.

8.3 Testing
8.3.2 Hydrostatic Tests
8.3.2.1
Add after first sentenc
e Minimum hydrotest pressure shall not be less than 150 kPa (20 psi).
Add new section
8.3.2.5
The minimum hold time of hydrotest pressure shall be 30 minutes.

8.3.3 Impeller Overspeed Test
8.3.3.2
Replace first sentence with
After the overspeed test, each impeller shall be examined by magnetic particle or liquid penetrant methods.
Add to section
Linear indications on the impeller shall not be acceptable.

8.3.4 Combined Mechanical and Performance Tests
Add new section heading
8.3.4.8 Lube Oil Flushing Test
Add new section
8.3.4.8.1 Lube oil flushing and cleanliness test shall be carried out using a 100 mesh stainless steel screen.
Add new section
8.3.4.8.2
The flushing test shall be performed at least 1 hour prior to the combined performance and mechanical run test, in accordance with the cleanliness standard as per ISO 4406-3 Grade 17/14 or SAE AS 4059 Class 8.
Add new section heading

8.3.4.9 Noise Test
Add new section
8.3.4.9.1
Noise tests shall be conducted as per ISO 2151-2 using sound intensity scanning method as per ISO 9614-2 and using a sound intensity system meeting the requirements of IEC 1043 Class 1.
Add new section
8.3.4.9.2
For multiple, identical compressor packages, it may be sufficient to carry out noise testing on only one compressor package.
Add new section
8.3.4.9.3
For vendor’s standard equipment, data from previous tests on identical equipment may be accepted, if agreed by the purchaser.
Add new section
8.3.4.9.4
Any safety margin required to cover for measurement uncertainty between the measured sound power level and guaranteed sound power level shall be specified by the purchaser.

8.4 Preparation for Shipment
Add new section
8.4.8
All exposed machined and un-coated surface shall be protected with vapour-proof corrosion inhibitor to protect against onset of corrosion.
Add new section
8.4.9
All visible display units and control panel front face shall be adequately protected against damage during transportation and handling
Add new section
8.4.10
The vendor shall provide completed preservation checklists and preservation report detailing all preservation activities performed.
Add new section
8.4.11
Provision for turning on the anti-condensation heater for motors while they are idle shall be clearly stated in the preservation procedure.
Add new section
8.4.12
Open pipes, flexible hoses, open tubes, etc. shall be blanked-off and capped with material of compatible metallurgy. Valves that are open to the atmosphere in the final installed position shall have their outboard connection either plugged or blinded.
Add new section heading

8.6 Control Panel Test
Add new section
8.6.1
The compressor control panel shall be functionally tested to verify correct functioning of control logic, alarms, shutdown functions and trip set points.
Add new section
8.6.2
The anti-surge controller shall be tested to verify the surge anticipation and surge detection algorithm. The anti-surge controller test procedure shall be developed and mutually agreed between the purchaser and the vendor.
Add new section
8.6.3
Control panel hard-wire verification testing and wiring continuity check on the skid shall be performed by the vendor and documented in the test report.

반응형